At 9:42 a.m. on January 4, 2019, the runner of the last wind turbine of Gaoyushan wind farm project located in Nan'an, Fujian province, the first EPC project undertaken by Fujian Yongfu Power Engineering Co.,Ltd (Yongfu), was successfully connected with the nacelle. A total of 24 wind turbines standing on the top ground of the Mountain Gaoyu marks the completion of the erection of all the wind turbines of this project, which has paved the way for subsequent grid interconnection and power generation.
Located in Gaoyushan, Dongtian Town, Nan'an City, the project is of an inland mountain wind farm consisting of 24 wind turbines with installed capacity of 70 MW. It is the first time for the adoption of 3 MW wind turbine for onshore wind farm built in Fujian province.
Since the commencement on May 26, 2017, Yongfu has been working hard with various contractors to provide best-in-class services under the guidance and support of the owner (China Nuclear Huineng Co. Ltd.) and the supervisor (the Fifth Research and Design Institute of Nuclear Industry). Yongfu vows to build a benchmark project in the power industry with the advantages of the EPC project.